Document
Details |
||||||||
Client Drainage Services Department |
||||||||
Project Contract No. DC/2007/24 Construction of Sewage Conveyance
System from |
||||||||
Document Title Baseline
Environmental Monitoring Report |
||||||||
Document No. GEN/026 |
||||||||
Distribution |
||||||||
Copy
No. |
Issued
To |
Copy
No. |
Issued
To |
|||||
01-02 |
Leighton-LNS
JV |
10 |
Metcalf
& Eddy-AECOM JV |
|||||
03 |
Mott
MacDonald Hong Kong Ltd |
11 |
ACL (Project
Office) |
|||||
04-08 |
EPD |
12 |
ACL (Head Office) |
|||||
09 |
DSD |
|
|
|||||
Submission
Ref |
Controlled
Copy No. |
|||||||
SUBM
Ref. |
|
|
||||||
Atkins
Ref.(s) |
DC/2007/24/31.20/OG0824/EC/SB/SC |
|
||||||
|
|
|
||||||
|
|
|
||||||
Revision
History |
||||||||
|
|
|
|
|
|
|||
|
|
|
|
|
|
|||
C |
30 Mar 2010 |
Submission to
IEC for Verification (upon comments on
Landscape and Visual Section) |
Various |
Susana Halliday |
Eric Chui |
|||
B |
9 Dec 2009 |
Submission
to IEC for Verification |
Various |
Susana Halliday |
Eric Chui |
|||
A |
8 Dec 2009 |
Submission
to IEC for Review |
Various |
Susana Halliday |
Eric Chui |
|||
Rev. |
Date |
Description |
Prepared |
Checked
& Reviewed |
Approved |
|||
|
|
Rev.
|
||||||
This Baseline
Environmental Monitoring Report has been prepared by Atkins China Ltd (ACL) for
Contract No. DC/2007/24 Construction of Sewage Conveyance System from
Apart from the construction works conducted by the Hong Kong West
Drainage Tunnel at the vicinity of Project Cyberport PTW site, no major
construction activities influencing air quality, noise or landscape and visual
aspects were identified during the baseline monitoring.
Air Quality
Baseline air quality monitoring
was undertaken at four representative sensitive receiver locations (CM_FM1
Western Wholesale Food Market, CM_CB1a The Arcade, Cyberport, CM_WF1a Wah Ming
House and CM_AB1a The Hong Kong Ice and Cold Storage). The baseline monitoring of air quality
included 1-hour and 24-hour TSP monitoring, which was undertaken from September
to December 2009, were ranged from 46 to 126mg/m3
and 68 to 90mg/m3 respectively. The baseline TSP monitoring data was
processed, reviewed and analysed to establish the Action Levels for 1-hour and
24-hour TSP Levels to be used during impact monitoring. The Limit Levels for 1-hour and
24-hour TSP Levels were based on the Project EM&A Manual.
Noise
Five locations (M3 Block A, Kwan Yick Building Phase III, M5 Chuk Lam Ming Tong, M6a Outside of Aegean Terrace, M7a Wah Ming House and M8 Wah Lai House) have been completed with the results presented in this Report. Baseline noise monitoring was conducted over period of at least two weeks at each location. Average Leq(30min) results for these five locations ranged from 57.3(A) to 69.1dB(A) during the daytime of normal weekdays and Leq(5min) ranged from 50.8dB(A) to 67.1dB(A) during restricted hours. Results from the monitoring work have been processed to establish baseline conditions. Action and Limit Levels were adopted from the Project EM&A Manual.
Landscape and Visual
Site
visits for the baseline landscape and visual monitoring were made on the 2
December 2009. No significant
changes between the existing and the baseline condition of landscape resources,
landscape characters areas and views towards visually sensitive receivers as
stipulated in the approved EIA were identified aside from:
ˇP
Change of landscape
resources of LR5 and LR7; and
ˇP
One removed VSR in
Two
trees were identified as missing at each of LR5 and LR7 and 1 dead tree was
identified at LR7. The compensation
of these missing/dead trees is under discussion with DLO. Except LR5 and LR7, no changes to the
landscape and visual mitigation measures as proposed in the approved EIA are
required.
CONTENTS
Page
1.1 Project Background Information
1.2 Purpose and Scope of the Baseline
Monitoring
2.3 Monitoring Parameters, Frequency
and Programme
2.4 Air Quality (Dust) Monitoring
Equipment
2.5 Methodology and QA/QC Procedure
3.3 Monitoring Parameters, Frequency
and Duration
3.4 Noise Monitoring Equipment
3.5 Methodology and QA/QC Procedure
4.2 Summary of Findings in Baseline
Landscape and Visual Monitoring Report
5 revision for inclusion in the em&A manual
6 conclusions and recommendations
List
of Tables
Table
2.1 List of Air Quality (Dust) Monitoring Locations
Table
2.2 Equipment Used for Dust Monitoring at CM_CB1a, CM_WF1a
and CM_AB1a
Table
2.3 Summary of Baseline 1-hour and 24-hour TSP Monitoring
Results
Table
2.4 Action and Limit Levels for Air Quality (Dust)
Table
2.5 Event/ Action Plan for Construction Air Quality
Table
3.1 List of Noise Monitoring Locations
Table
3.2 Baseline Noise Monitoring Programme
Table
3.3 Noise Monitoring Equipment
Table
3.4 Summary of Baseline Noise Monitoring Results
Table
3.5 Action and Limit Levels for Noise
Table
3.6 Event/ Action Plan for Construction Noise
Table
4.1 Key Visually Sensitive Receivers (VSRs)
Table
4.2 Updated Information on Landscape Resources
Table
4.3 Landscape Resources with Changed Status
Table
4.4 Event and Action Plan for Landscape and Visual Impact -
Construction Phase
List
of Figures
Figure 1.1 Overall Layout Plan
Figure 2.1 Construction Dust Monitoring Station at Fung Mat Road Site
Figure 2.2 Construction Dust Monitoring Station at Cyberport PTW
Figure 2.3 Construction Dust Monitoring Station at Wah Fu PTW and Aberdeen PTW
Figure 3.1 Construction Noise Monitoring Station at Fung Mat Road Site
Figure 3.2 Construction Noise Monitoring Station at Sandy Bay PTW
Figure 3.3 Construction Noise Monitoring Station at Cyberport PTW
Figure 3.4 Construction Noise Monitoring Station at Wah Fu PTW and Aberdeen PTW
Appendices
Appendix A1 Baseline Air Quality Monitoring Schedule
Appendix A2 Calibration Certificates for Air Quality Monitoring Equipment
Appendix A3 Baseline Air Quality Monitoring Results
Appendix B1 Baseline Noise Monitoring Schedule
Appendix B2 Calibration Certificates for Noise Monitoring Equipment
Appendix B3 Baseline Noise Monitoring Data
Appendix C Weather Condition during Baseline Monitoring Period
Appendix D Baseline Landscape and Visual Monitoring Report
Appendix E Construction Programme
Appendix F Response to Comments
The sewerage tunnels to be constructed under Contract No. DC/2007/24 ˇ§Harbour Area Treatment Scheme Stage 2A Construction of Sewage Conveyance
System from
The purpose of this
Report is to establish the ambient environmental conditions (including air
quality, noise as well as landscape and visual aspects) from 25 September 2009 to
4 December 2009, prior to the commencement of the Project construction works in
accordance with the requirements of the Project EM&A Manual. The baseline conditions will be used as
the basis for environmental impact monitoring during construction.
As part of the requirements
under EP, the Baseline Environmental Monitoring Report should be verified by
the Independent Environmental Checker (IEC) and submitted to the Director of
Environmental Protection (DEP) at least 2 weeks before the commencement of the
project construction.
ˇP
Section 2 ˇV Air
Quality
ˇP
Section 3 ˇV Noise
ˇP
Section 4 ˇV Landscape
and Visual
In accordance with the Project
EM&A Manual, baseline air quality monitoring should be conducted at representative
sensitive receiver locations for a period of at least fourteen days, in terms
of 1-hour and 24-hour Total Suspended Particulates (TSP). Monitoring of 1-hour TSP was carried out
three times per day while that of 24-hour TSP was conducted once everyday for
14 consecutive days.
Monitoring location CM_FM1 Western
Wholesale Food Market locates at the interface area of this Project and
Contract DC/2007/23, baseline air quality monitoring was conducted by the ET of
Contract DC/2007/23 and relevant data is adopted in this Report.
Baseline
air quality monitoring was conducted at three (3) other monitoring stations. Figures 2.1 to 2.3 illustrate the
locations of monitoring locations under this Project and relevant descriptions
are provided in Table
2.1. The
exact locations of these monitoring stations were changed from the Project
EM&A Manual and such revision was approved by EPD.
Table 2.1 List of Air Quality (Dust)
Monitoring Locations
Monitoring ID |
Description |
Location of Measurement |
Figure Reference |
CM_FM1 (1) |
Western Wholesale Food Market ( |
Podium |
|
CM_CB1a (2) |
The (Cyberport PTW) |
Ground level at children
playground, adjacent to Project site office |
|
CM_WF1a (2) |
Wah Ming House (Wah Fu PTW) |
Roof |
|
CM_AB1a (2) |
The Hong Kong Ice and Cold Storage, formally
known as Dairy Farm Ice and Cold Storage ( |
1.5m raised platform at car park |
Note: (1) Baseline
air quality monitoring was conducted by ET of Contact DC/2007/23 and data is
adopted in this Report.
(2) Revision
to the original monitoring locations in Project EM&A Manual was made and
was verified by IEC on 19 November 2009 and subsequently approved by EPD on 27
November 2009.
The
baseline TSP monitoring was conducted between
The
detail baseline air quality monitoring schedule for all locations is provided
in Appendix A1.
All the
equipment used was in accordance with the Baseline Environmental Monitoring
Plan Rev C approved by IEC on 19 November 2009.
For baseline air quality
monitoring at CM_FM1 Western Wholesale Food Market, both 1-hour TSP and 24-hour
TSP were conducted using High Volume Sampler (HVS) by ET of Contact
DC/2007/23. Details of the
monitoring equipment are provided in Contract No. DC/2007/23 ˇV Harbour Area
Treatment Scheme Stage 2A Construction of Sewage Conveyance System from North Point
to
For
baseline air quality monitoring at other 3 locations, 1-hour TSP air quality
monitoring was performed using 1-hour dust meter and continuous 24-hour TSP
monitoring was performed using High Volume Sampler (HVS) associated with
equipment and shelter complied with the specifications stipulated in the
approved EM&A Manual. Table 2.2 summarizes the equipment used in the baseline air
quality monitoring at these 3 locations.
All monitoring equipment was checked and calibrated prior to use. Copies of the calibration certificates
for the equipment are presented in Appendix A2.
Table 2.2 Equipment Used for Dust Monitoring at
CM_CB1a, CM_WF1a and CM_AB1a
Parameter Measured |
Equipment |
1-hour TSP Sampling |
Sibata Laser Dust
Monitor Model LD-3B was used for monitoring stations CM_CB1a, CM_WF1a and CM_AB1a. This portable instrument
is capable of providing: ˇP
Real time TSP concentration ˇP
Adjustable
logging intervals from ˇP
Average
concentration over logging interval and maximum and average values for entire
logging period |
24-hour TSP Sampling |
A High Volume Sampler
Model TE-5170, by Tisch Environmental, Inc., was used for monitoring stations
CM_CB1a, CM_WF1a and CM_AB1a. This instrument was
equipped with: ˇP
Mass flow controller with 20 ˇV 60 SCFM adjustable
flow probe ˇP
Mechanical timer for recording elapsed-time and
24-hour operation ˇP
A continuous flow recorder for continuous
monitoring |
Weather
data (wind speed) from the Green Island (for CM_FM1 and CM_CB1a) and Wong Chuk
Hang (for CM_WF1a and CM_AB1a) weather stations of the Hong Kong Observatory
during the baseline monitoring period are shown in Appendix C. The general weather conditions (i.e.
sunny, cloudy, or rainy) were recorded by the field observation on the
monitoring day.
HVS Installations
The following criteria were
considered in the installation of the HVS:
ˇP
a horizontal platform
with appropriate support to secure the samplers against gusty wind was
provided;
ˇP
no two HVS were placed
less than 2m apart;
ˇP
the distance between
the HVS and any obstacles, such as buildings, was at least twice the height
that the obstacle protrudes above the HVS;
ˇP
a minimum of 2m
separation from walls, parapets and penthouses was required for rooftop
samplers;
ˇP
a minimum of 2m
separation from any supporting structure, measured horizontally;
ˇP
no furnace or
incinerator flues were nearby;
ˇP
airflow around the
sampler was unrestricted;
ˇP
any wire fence and
gate, to protect the sampler did not cause any obstruction during monitoring;
ˇP
permission was obtained
to set up the samplers and to obtain access to the monitoring stations; and
ˇP
a secured supply of electricity
was provided to operate the samplers.
Field Measurements
At each monitoring location, 24-hour TSP
measurements were undertaken using a HVS in accordance with the specifications
listed in the EM&A Manual. Each
HVS included a motor, a filter holder, a flow controller and a sampling inlet
in accordance with the performance specification of the USEPA Standard Title
40, Code of Federation Regulations Chapter 1 (Part 50), Appendix B.
The following activities were undertaken
during the HVS monitoring:
ˇP
the power supply was
checked to ensure the HVS works properly;
ˇP
the filter holder and
the area surrounding the filter were cleaned;
ˇP
the filter holder was
removed by loosening the four bolts and a new filter on a supporting screen was
aligned carefully;
ˇP
the filter was properly
aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter;
ˇP
the swing bolts were
fastened to hold the filter holder down to the frame. The pressure applied was sufficient to
avoid air leakage at the edges;
ˇP
the shelter lid was
closed and was secured with the aluminum strip;
ˇP
the HVS was warmed-up
to establish run-temperature conditions;
ˇP
a new flowrate record
sheet was set into the flow recorder;
ˇP
the programmable timer
was set for a sampling period of 24 hrs + 1 hr, and the starting time, weather
condition and the filter number were recorded;
ˇP
the initial elapsed
time was recorded;
ˇP
at the end of sampling,
the sampled filter was removed carefully and folded in half-length so that only
surfaces with collected particulate matter were in contact;
ˇP
the sample was placed
in a clean plastic envelope and sealed;
ˇP
all monitoring
information was recorded on a standard data sheet; and
ˇP
the filters were taken
back to laboratory for analysis.
The measuring procedures of the
1-hour dust meter are in accordance with the Manufacturerˇ¦s Instruction Manual
as follows:
ˇP
the 1-hour dust meter
is placed at least 1.3m above ground;
ˇP
set POWER to ˇ§ONˇ¨ and
make sure that the battery level was not flash or in low level;
ˇP
pull the air sampling
inlet cover up;
ˇP
push the knob at
MEASURE position;
ˇP
set time/mode setting
to [BG] by pushing the time setting switch. Then, start the background measurement
by pushing the start/stop switch once.
It will take 6 sec. to complete the background measurement;
ˇP
turn knob to SENSI. ADJ
position and press in;
ˇP
push Start/Stop switch
once;
ˇP
gently return knob to
the MEASURE position;
ˇP
push the time setting
switch to change the time setting display to [LOG] at the bottom left of the
liquid crystal display;
ˇP
remove the cap and
start measurement; and
ˇP
information such as
sampling date, time, count value and site condition were recorded during the
monitoring period.
Laboratory
Measurement/Analysis
The
TSP samples collected from HVS at CM_CB1a, CM_WF1a and CM_AB1a were analysed at
the ETˇ¦s in-house Laboratory at Central Reclamation III. The methodology and analysis at the
laboratory was approved by the Engineerˇ¦s Representative (ER) in consultation
with the IEC.
Clean
filter paper with no folds or pin holes of size 8ˇ¨ x 10ˇ¨ were labelled before
sampling. The filter paper were
conditioned in a humidity-controlled chamber for over 24 hours and pre-weighed
before used for sampling. After sampling, the filter paper containing the dust
was kept tightly sealed in a plastic bag.
The filter was then returned to the laboratory for reconditioning in a
humidity-controlled chamber followed by accurate weighing by an electronic
balance.
The
weather during the monitoring period included a variety of conditions: fine, cloudy,
rainy and sunny weather. 24-hour
TSP sampling at CM_FM1a Wah Ming House was suspended between 19 November to 22
November 2009 due to equipment malfunctioning. Additional measurements were undertaken
to make up for the days that sampling could not be undertaken.
The
baseline monitoring results at all monitoring locations are provided in full in
Appendix A3. The summary of the baseline data at each
monitoring location in terms of average, minimum and maximum value for 1-hour
and 24-hour TSP sampling are summarised in Table
2.3.
Graphical representations of the 1-hour and 24-hour TSP sampling results
are also shown in Appendix A3. Detailed weather conditions during the
baseline monitoring period are shown in Appendix C.
Table 2.3 Summary of Baseline 1-hour and 24-hour TSP
Monitoring Results
Monitoring ID |
Average 1-hour TSP Concentration, µg/m3 (Range) |
Average 24-hour TSP Concentration, µg/m3 (Range) |
CM_FM1 (1) |
126 (61 - 201) |
90 (50 - 147) |
CM_CB1a |
46 (15 - 96) |
74 (41 ˇV 125) |
CM_WF1a |
53 (11 - 119) |
85 (47 ˇV 128) |
CM_AB1a |
50 (15 - 117) |
68 (40 ˇV 91) |
Note: (1) Baseline
air quality monitoring was conducted by ET of Contact DC/2007/23 and data is
adopted in this Report.
For
Fung Mat Road Site of this Project, the average 1-hour and 24-hour TSP
concentrations measured at CM_FM1 Western Wholesale Food Market were 126mg/m3 and 90mg/m3 respectively. Weather during baseline monitoring
period was fine or sunny except 28-30 September 2009, which was rainy. Major dust source identified was road
traffic dust from
For
Cyberport PTW site of this Project, the average 1-hour and 24-hour TSP
concentrations measured at CM_CB1a The Arcade, Cyberport were 46mg/m3 and 74mg/m3 respectively. Weather during baseline monitoring
period was cloudy/ fine/ sunny. Dust
source identified was construction dust from the Hong Kong West Drainage Tunnel
next to the Project Cyberport PTW site.
For
Wah Fu PTW site of this Project, the average 1-hour and 24-hour TSP
concentrations measured at CM_WF1a Wah Ming House were 53mg/m3 and 85mg/m3 respectively. Due to HVS malfunction, baseline
monitoring was suspended between 19-22 November 2009. Weather during baseline monitoring
period was cloudy/ fine/ sunny. No
major dust source was identified.
For
Aberdeen PTW site of this Project, the average 1-hour and 24-hour TSP
concentrations measured at CM_AB1a The Hong Kong Ice and Cold Storage were 50mg/m3 and 68mg/m3 respectively. Weather during baseline monitoring
period was cloudy/ fine/ sunny. No
major dust source was identified.
Action and Limit Levels for air
quality were set in accordance with the EM&A Manual. The Action and Limit Levels for all
monitoring locations are provided in Table
2.4.
Table 2.4 Action and Limit Levels for Air Quality
(Dust)
Monitoring ID |
1-hour TSP Level, µg/m3 |
24-hour TSP Level, µg/m3 |
||
Action |
Limit |
Action |
Limit |
|
CM_FM1 |
332 (1) |
500 |
188 (2) |
260 |
CM_CB1a |
280 (1) |
500 |
178 (2) |
260 |
CM_WF1a |
285 (1) |
500 |
185 (2) |
260 |
CM_AB1a |
283 (1) |
500 |
174 (2) |
260 |
Notes:
(1)
For
Baseline Level £ 384 mg/m3, Action Level = (Baseline Level*1.3 + Limit Level)/2;
For
Baseline Level > 384 mg/m3, Action Level = Limit Level
(2) For Baseline
Level £ 200 mg/m3, Action Level = (Baseline Level*1.3 + Limit Level)/2;
For
Baseline Level > 200 mg/m3, Action Level = Limit Level
The Event and Action Plan in the
event of an exceedance of the above Action and Limit Levels are provided in Table 2.5 below.
Table 2.5 Event/ Action Plan for Construction Air
Quality
Action |
||||
ET |
IEC |
ER |
Contractor |
|
ACTION
LEVEL |
||||
1. Exceedance for one sample |
1. Identify source, investigate the causes of
exceedance and propose remedial measures; 2.
Inform
IEC and ER; 3.
Repeat
measurement to confirm finding; 4. Increase monitoring frequency to daily. |
1. Check monitoring data submitted by ET; 2. Check Contractorˇ¦s working method. |
1. Notify Contractor. |
1. Rectify
any unacceptable practice; 2. Amend working methods if
appropriate. |
2. Exceedance for two or more
consecutive samples |
1. Identify source; 2.
Inform
IEC and ER; 3.
Advise
the ER on the effectiveness of the proposed remedial measures; 4.
Repeat
measurements to confirm findings; 5.
Increase
monitoring frequency to daily; 6.
Discuss with IEC and Contractor
on remedial actions required; 7.
If
exceedance continues, arrange meeting with IEC and ER; 8. If exceedance stops, cease additional
monitoring. |
1. Check monitoring data submitted by ET; 2.
Check
Contractorˇ¦s working method; 3.
Discuss
with ET and Contractor on possible remedial measures; 4.
Advise
the ET on the effectiveness of the proposed remedial measures; 5. Supervise Implementation of remedial measures. |
1. Confirm
receipt of notification of failure in writing; 2.
Notify
Contractor; 3.
Ensure
remedial measures properly implemented. |
1. Submit
proposals for remedial to ER within 3 working days of notification; 2. Implement
the agreed proposals; 3. Amend proposal if
appropriate. |
LIMIT
LEVEL |
||||
1. Exceedance for one sample |
1. Identify
source, investigate the causes of exceedance and propose remedial measures; 2. Inform
ER, Contractor and EPD; 3. Repeat
measurement to confirm finding; 4. Increase
monitoring frequency to daily; 5. Assess effectiveness of
Contractorˇ¦s remedial actions and keep IEC, EPD and ER informed of the results. |
1. Check monitoring data submitted by ET; 2.
Check
Contractorˇ¦s working method; 3.
Discuss
with ET and Contractor on possible remedial measures; 4.
Advise
the ER on the effectiveness of the proposed remedial measures; 5. Supervise implementation of remedial measures. |
1. Confirm receipt of notification of failure in
writing; 2.
Notify
Contractor; 3. Ensure remedial measures properly implemented. |
1. Take immediate action to avoid further
exceedance; 2.
Submit
proposals for remedial actions to IEC within 3 working days of notification; 3.
Implement
the agreed proposals; 4. Amend proposal if
appropriate. |
2. Exceedance for two or more
consecutive samples |
1. Notify IEC, ER, Contractor and EPD; 2.
Identify
source; 3.
Repeat
measurement to confirm findings; 4.
Increase
monitoring frequency to daily; 5.
Carry
out analysis of Contractorˇ¦s working procedures to determine possible
mitigation to be implemented; 6.
Arrange
meeting with IEC and ER to discuss the remedial actions to be taken; 7.
Assess
effectiveness of Contractorˇ¦s remedial actions and keep IEC, EPD and ER
informed of the results; 8. If exceedance stops, cease additional
monitoring. |
1. Check monitoring data submitted by ET; 2.
Check
Contractorˇ¦s working method; 3.
Discuss
amongst ER, ET, and Contractor on the potential remedial actions; 4.
Review
Contractorˇ¦s remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly; 5. Supervise the implementation of remedial
measures. |
1. Confirm receipt of notification of failure in
writing; 2.
Notify
Contractor; 3.
In
consolidation with the IEC, agree with the Contractor on the remedial
measures to be implemented; 4.
Ensure
remedial measures properly implemented; 5. If exceedance continues, consider what portion
of the work is responsible and instruct the Contractor to stop that portion
of work until the exceedance is abated. |
1. Take
immediate action to avoid further exceedance; 2. Submit
proposals for remedial actions to IEC within 3 working days of notification; 3. Implement
the agreed proposals; 4. Resubmit
proposals if problem still not under control; 5. Stop the relevant portion
of works as determined by the ER until the exceedance is abated. |
Baseline noise monitoring was conducted at least 14 days at the monitoring locations between 25 September 2009 and 30 November 2009 prior to the commencement of construction. The baseline monitoring was carried out daily for a period for at least 2 weeks. The baseline noise monitoring programme was provided in the Baseline Environmental Monitoring Plan Rev C approved by IEC on 19 November 2009. Logger function check and calibration was carried out according to manufacturerˇ¦s recommendations. The equipment was checked and inspected not less than once every two days after the set up at each monitoring station.
Monitoring location M3 Block A, Kwan
Yick Building Phase III locates at the interface area of this Project and
Contract DC/2007/23, baseline noise monitoring was conducted by the ET of Contract
DC/2007/23 and relevant data is adopted in this Report.
Five (5) monitoring locations have been identified for noise
monitoring for the Project. Figures
3.1 to 3.4 show the locations of the monitoring stations and the proposed above
ground works area. Table 3.1 presents a list of the monitoring locations. The exact locations at Aegean Terrace
(M6a) and Wah Ming House (M7a) were changed from the Project EM&A Manual
and such revision was approved by EPD.
Table 3.1 List of Noise Monitoring Locations
Monitoring ID |
Location |
Use |
Façade / free field measurement |
Figure Reference |
M3 (1) |
Rooftop (24/F) of Block A, ( |
Medium-rise
domestic premises ˇV private housing estate |
Façade |
|
M5 |
Rooftop (4/F) of Chuk Lam Ming Tong ( |
Hospital and
clinics - home for the aged |
Façade |
|
M6a (2) |
2m above ground, outside of Aegean Terrace (Cyberport PTW) |
Low-rise
domestic premises ˇV private housing |
Free field (3) |
|
M7a (2) |
Rooftop (19/F) of Wah Ming House (Wah Fu PTW) |
Medium-rise
domestic premises ˇV public housing estate |
Façade |
|
M8 |
Roof (39/F) of Wah Lai House ( |
High-rise
domestic premises ˇVpublic housing estate |
Façade |
Note: (1) Baseline
noise monitoring was conducted by ET of Contact DC/2007/23 and data is adopted
in this Report.
(2) Revision to the
original monitoring locations laid out in Project EM&A Manual was made and
was verified by IEC on
(3) A
correction factor of +3dB(A) will be added from free field to façade
measurement
LAeq as well as L10 and L90
were recorded at 5-minute intervals during the restricted hours of evening and
night-time hours, and during the daytime of Sundays and public holidays; and
30-minute intervals were recorded during daytime hours on normal weekdays.
Monitoring periods for all five monitoring locations are
listed below:
ˇP
M3: 25-28 September 2009 and 7-19
October 2009 (suspension between 29 September and 1 October 2009 as well as 2
to 6 October due to bad weather and relocation of noise meter respectively)
ˇP
M5: 27 October to 10 November
2009
ˇP
M6a: 13 to 27 November 2009
ˇP
M7a: 17 to 30 November 2009
ˇP
M8: 23 October to 6 November 2009
Detail baseline noise monitoring schedule is provided in Appendix B1. When suspension of monitoring due to
different reasons at monitoring locations M3 and M6a, monitoring schedule was
extended to fulfil the monitoring period required under Project EM&A
Manual. Data obtained from baseline noise
monitoring is presented according to the following time periods:
ˇP
Daytime:
ˇP
Evening-time:
ˇP
Night-time:
The frequencies and parameters of baseline monitoring are
shown in Table
3.2
Table 3.2
Baseline Noise Monitoring Programme
Time
Period |
Duration,
min |
Parameters |
Daytime: |
30 |
Leq,
L90 & L10 |
Daytime of
Sundays/ Public Holiday and Evening-time |
5 |
|
Night-time: |
Two Integrated Sound Level Meters (SLMs) were used for noise
monitoring. The noise meter was a
Type 1 sound level meter capable of giving a continuous readout of the noise
level readings including equivalent continuous sound pressure level (Leq)
and percentile sound pressure level (Lx). The SLM complied with
International Electrotechnical Commission Publications 651:1979 (Type 1) and
804:1985 (Type 1). Table 3.3 summarises the noise monitoring equipment model
used. Certificate of Conformance of
the SLMs and calibrator are given in Appendix B1.
Table 3.3 Noise Monitoring Equipment
Equipment |
Model |
Integrated Sound Level Meters |
B&K 2238 Serial nos. 2684502 and 2684503 |
Calibrator |
B&K 4231, Serial no. 2385180 |
The following procedures were followed during the noise
monitoring:
ˇP
the monitoring station
was set approximately 1 m from the exterior of the noise sensitive receiver
building façade or at least 1.2 m above the ground for free-field measurements;
ˇP
the battery condition
was checked to ensure good functioning of the meter;
ˇP
parameters such as
frequency weighting, time weighting, and measurement time were set as follows:
¨
frequency weighting ˇV A
¨
time weighting ˇV fast
¨
time measurement ˇV 5
minutes
ˇP
prior to and after the
noise measurement, the meter was calibrated using the Calibrator for 94 dB at
1000 Hz. There was no recorded difference in the calibration level before and
after measurement of more than 1 dB(A);
ˇP
all noise quality
monitoring was conducted with the wind speed not exceeding 5m/s and no gusts
exceeding 10m/s (see Appendix C for mean wind speed); and
ˇP
all noise quality
monitoring was conducted in accordance with the methodology specified in the
Project EM&A Manual.
The results from baseline noise monitoring at all locations are
presented in this section.
The weather during the monitoring included dry, cloudy, fine
and sunny conditions. Apart from construction activities from Hong Kong West
Drainage Tunnel next to the Project Cyberport PTW site, which is in the
vicinity of M6a Outside of Aegean Terrace, no construction activities were
identified in the vicinity of the monitoring locations that may influence the
baseline monitoring results.
Road traffic from Connaught Road West and slip roads to
Western Harbour Crossing was the major noise source in area of M3 (Block A,
Kwan Yick Building Phase III).
Whereas traffic noise from Sandy Bay Road/ Sha Wan Drive, Waterfall Bay
Road, Wah Kwan Road/ Tin Wan Praya Road were the major noise sources in area M5
(Chuk Lam Ming Tong), M7a (Wah Ming House) and M8 (Wah Lai House)
respectively. For M6a (Outside of
Aegean Terrace), the major noise source were traffic noise from Sassoon Road/ Cyberport
Road and construction activities from the Hong Kong West Drainage Tunnel.
Anomalies in noise
measurements due to periods of external factors were not used in analysis of
the baseline noise condition. The
baseline monitoring results (raw data and graphical presentation) from the
monitoring stations are provided in full in Appendix B2. A summary of the
baseline data (minimum, maximum and average) with anomalies (external factors)
and without anomalies is shown in Table
3.4. As free-field measurement was made for M6a, a
+3dB(A) correction factor has been applied to these results.
Table 3.4 Summary of Baseline Noise Monitoring
Results
Monitoring
ID |
Leq
(30 mins), dB(A) |
Leq (5 mins), dB(A) |
||
Daytime
|
Daytime
|
Evening
time |
Night-time
|
|
M3 (2) |
Min to Max: 65.8 ˇV 75.9 (75.2) |
Min to Max: 63.0 ˇV 71.6 |
Min to Max: 64.4 ˇV 70.6 |
Min to Max: 57.2 ˇV 70.3 |
|
Average: 69.2 (69.1) |
Average: 67.1 |
Average: 66.9 |
Average: 62.5 |
M5 |
Min to Max: 59.0 ˇV 73.4 (67.7) |
Min to Max: 55.1 ˇV 75.2 (69.8) |
Min to Max: 56.2 ˇV 63.6 |
Min to Max: 54.4 ˇV 70.2
(68.8) |
|
Average: 63.1 |
Average: 59.2 (59.1) |
Average: 58.9 |
Average: 56.6 |
M6a (3) |
Min to Max: 51.2 ˇV
67.8 |
Min to Max: 47.5 ˇV 70.0 (62.6) |
Min to Max: 46.1 ˇV 78.2 (65.9) |
Min to Max: 41.6 ˇV 67.0 |
|
Average: 57.3 |
Average: 53.7 (53.6) |
Average: 52.4 (52.3) |
Average: 50.8 |
M7a |
Min to Max: 55.4 ˇV 70.3 |
Min to Max: 54.6 ˇV 66.1 |
Min to Max: 51.9 ˇV 64.6 |
Min to Max: 46.8 ˇV 66.1 |
|
Average: 59.2 |
Average: 58.4 |
Average: 56.2 |
Average: 54.2 |
M8 |
Min to Max: 62.0 ˇV 65.5 |
Min to Max: 59.6 ˇV 66.2 |
Min to Max: 60.1 ˇV 65.2 |
Min to Max: 52.5 ˇV 64.4 |
|
Average: 64.0 |
Average: 62.4 |
Average: 60.2 |
Average: 57.9 |
Note (1) Figures
in parentheses ( ) indicate results including anomalies from rainstorms and
external factors
(2) Baseline
noise monitoring was conducted by ET of Contact DC/2007/23 and data is adopted
in this Report.
(3) A
correction factor of +3dB(A) will be added from free field to façade
measurement
The Action and Limit Levels of noise were established in
accordance with the EM&A Manual and are provided in Table 3.5.
Table 3.5 Action and Limit Levels for Noise
Time Period |
Action |
Limit |
0700-1900 hrs on normal weekdays |
When one documented complaint is received |
75dB(A)(1) |
0700-2300 hrs on holidays and 1900-2300 hrs
on all other days |
60/65/70dB(A)(2) |
|
2300-0700 of next day |
45/50/55dB(A)(2) |
Note:
(1) Between
0700-1900, construction noise limit for school during normal term time is
70dB(A) and 65dB(A) during examination period.
(2)
To be
selected based on Area Sensitivity Rating
The Event and Action Plan in the event of an exceedance of
the above Action and Limit Levels are provided in Table 3.6 below.
Table 3.6 Event/ Action Plan for Construction Noise
Action |
||||
ET |
IEC |
ER |
Contractor |
|
Action Level being exceeded |
1.
Notify ER, IEC and Contractor; 2.
Carry out investigation; 3.
Report the results of investigation to the
IEC, ER and Contractor; 4.
Discuss with the IEC and Contractor on
remedial measures required; 5.
Increase monitoring frequency to check
mitigation effectiveness. |
1.
Review the investigation results submitted by
the ET; 2.
Review the proposed remedial measures by the
Contractor and advise the ER accordingly; 3.
Advise the ER on the effectiveness of the
proposed remedial measures. |
1.
Confirm receipt of notification of failure in
writing; 2.
Notify Contractor; 3.
In consolidation with the IEC, agree with the
Contractor on the remedial measures to be implemented; 4.
Supervise the implementation of remedial
measures. |
1. Submit noise mitigation proposals to IEC and ER; 2. Implement noise mitigation proposals. |
Limit Level being exceeded |
1.
Inform IEC, ER, Contractor and EPD; 2.
Repeat measurements to confirm findings; 3.
Increase monitoring frequency; 4.
Identify source and investigate the cause of
exceedance; 5.
Carry out analysis of Contractorˇ¦s working
procedures; 6.
Discuss with the IEC, Contractor and ER on
remedial measures required; 7.
Assess effectiveness of Contractorˇ¦s remedial
actions and keep IEC, EPD and ER informed of the results; 8.
If exceedance stops, cease additional
monitoring. |
1.
Discuss amongst ER, ET, and Contractor on the
potential remedial actions; 2.
Review Contractorˇ¦s remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly. |
1.
Confirm receipt of notification of failure in
writing; 2.
Notify Contractor; 3.
In consolidation with the IEC, agree with the
Contractor on the remedial measures to be implemented; 4.
Supervise the implementation of remedial
measures; 5.
If exceedance continues, consider stopping the
Contractor to continue working on that portion of work which causes the
exceedance until the exceedance is abated. |
1.
Take immediate action to avoid further
exceedance; 2.
Submit proposals for remedial actions to IEC
and ER within 3 working days of notification; 3.
Implement the agreed proposals; 4.
Submit further proposal if problem still not
under control; 5.
Stop the relevant portion of works as
instructed by the ER until the exceedance is abated. |
The
baseline monitoring with respect to landscape and visual aspect was carried in
reference to the recorded baseline condition of the Project site as described
in Section 13 of the approved EIA Report under EIA Register No. AEIAR-121/2008.
The
baseline monitoring was conducted on 2 December 2009 by a subconsultant, namely
Environmental Resources Management, and the Baseline Landscape and Visual
Monitoring Report, which included monitoring parameters, monitoring schedule,
monitoring procedures and locations as well as results and observations, is attached in Appendix
D.
The
landscape resources (LRs), landscape character areas (LCAs) and viewing
condition of Visually Sensitive Receivers (VSRs) as summarized below as
summarized below:
Landscape
Resource (LR)
•
LR3 ˇV Trees on
•
LR4 ˇV Trees on PTW and temporary works area at
•
LR5 ˇV Trees on PTW and temporary works area at Cyberport
•
LR6 ˇV Trees on PTW at Wah Fu
•
LR7 ˇV Trees on PTW and temporary works areas at
Landscape
Character Area (LCA)
•
LCA1 ˇV Miscellaneous Urban Fringe Landscape
•
LCA2 ˇV Residential Urban Landscape
•
LCA3 ˇV City Grid Mixed Urban Development
•
LCA4 ˇV Residential Urban Fringe Landscape
•
LCA5 ˇV
•
LCA8 ˇV Organic Mixed Urban Development
•
LCA9 ˇV Coastal
•
LCA10 ˇV Settled Valley Landscape
•
LCA11 ˇV Transportation Corridor Landscape
•
LCA12 ˇV Industrial Urban Landscape
•
LCA13 ˇV Mixed Modern Comprehensive Urban Development Landscape
Visually Sensitive Receivers (VSRs)
Table 4.1 lists the key VSRs found within the Zone of Visual
Influence (ZVI).
Table 4.1
Key Visually Sensitive Receivers (VSRs)
ID. No. |
Key Visually Sensitive
Receivers (VSRs) |
Type of VSRs (a) |
Sai Ying Pun Area |
||
CR3.7 |
|
Commercial/ Residential |
CR3.8 |
|
Commercial/ Residential |
CR3.9 |
158A-162 |
Commercial/ Residential |
CR3.10 |
|
Commercial/ Residential |
GIC3.4 |
|
Recreational |
OU3.3 |
Western Wholesale Market |
Commercial |
T3.1 |
|
Transportation |
T3.2 |
|
Transportation |
|
||
CR4.1 |
Residential Block on Sha Wan Drive |
Residential |
GIC4.1 |
Canossian Retreat House |
Government / Institution / Community |
GIC4.2 |
Duchess of |
Government / Institution / Community |
GIC4.3 |
|
Government / Institution / Community |
GIC4.4 |
|
Government / Institution / Community |
GIC4.5 |
HKU |
Recreational |
OU4.1 |
|
Government / Institution / Community |
O4.1 |
|
Recreational |
T4.1 |
|
Transportation |
T4.2 |
Sea Travellers of |
Transportation |
Cybeport Area |
||
R5.1 |
|
Residential |
R5.2 |
|
Residential |
OU5.1 |
Cyber Centre |
Commercial/ Residential |
OU5.2 |
Bel-air |
Commercial/ Residential |
T5.1 |
|
Transportation |
T5.2 |
Sea Travellers of |
Transportation |
Wah Fu Area |
||
R6.1 |
Wah Fu Estate |
Residential |
O6.1 |
|
Recreational |
T6.1 |
|
Transportation |
T6.2 |
Sea Travellers of Pok Po Wan |
Transportation |
|
||
R7.1 |
Wah Kwai Estate |
Residential |
R7.2 |
Residential Zone on Ap Lei Chau Estate |
Residential |
I7.1 |
Gas Station |
Occupational |
I7.2 |
Industries Zone on |
Occupational |
OU7.1 |
Concrete Batching Plant, Planned Coach
Parking Area |
Occupational |
T7.1 |
Tin Wan |
Transportation |
T7.2 |
|
Transportation |
Note (a) R
= Residential; C = Commercial, CR = Commercial/Residential,
GIC
= Government/Institution/Community, O = Open space, OU = Others use; T =
Transport related.
Landscape
Resources (LR)
The
updated information on LRs is summarized in Table
4.2 and the change status of the LR5 and LR7 is presented
in Table
4.3.
Table 4.2
Updated Information on Landscape Resources
LR |
Name of LR |
No. of Trees
identified in EIA Report |
No. of Trees
estimated to be affected in the EIA Report |
Updated No. of Trees
Identified within Project Worksites during Baseline Monitoring (a) (b)
(c) |
LR3 |
Trees on |
0 |
0 |
0 |
LR4 |
Trees on PTW and temporary works area at
|
43 |
34 |
43 |
LR5 |
Trees
on PTW and temporary works area at Cyberport |
26 |
19 |
24 |
LR6 |
Trees on PTW at Wah Fu |
4 |
0 |
4 |
LR7 |
Trees on PTW and temporary works areas
at |
69 |
39 |
67 |
Notes: (a) Site boundaries
of work sites in the Project have updated from the boundaries stated in the
approved EIA report
based on current site conditions.
(b) Tree
Survey Report provided by Leighton-LNS JV is also referenced.
(c) Updated
No. of Trees includes all existing trees (status alive or dead) physically
found on site during site visits.
Table 4.3
Landscape Resources with Changed Status
LR |
Name of LR |
Tree No. |
Tree Species |
Estimated Size |
From |
Health |
Amenity Value |
Survival Rate after
Transplant |
Previous Status in Tree Survey Report |
Updated Status |
||
Height (m) |
DBH (mm) |
Spread (m) |
Good/ Fair/ Poor |
Good/ Fair/ Poor |
High/ Med/ Low |
High/ Med/ Low |
|
|
||||
LR5 |
Trees on PTW and
temporary works area at Cyberport |
T015 |
Archontophoenix alexandrae |
4.5 |
150 |
1.8 |
F |
F |
M |
H |
Transplanted |
Missing (a) |
T016 |
5 |
150 |
1.8 |
F |
F |
M |
H |
Transplanted |
Missing (a) |
|||
LR7 |
Trees on PTW and temporary works areas at |
T002 |
Acacia confusa |
5.1 |
200 |
5.5 |
P |
P |
L |
L |
Retained |
Missing (c) |
T008 |
Macaranga tanarius |
4 |
200 |
3 |
P |
P |
L |
L |
Transplanted |
Dead (b) |
||
T082 |
5.5 |
230 |
3 |
P |
P |
L |
L |
Retained |
Missing (a) |
Notes: (a) Reported missing on 9 October 2009. Refer to a letter dated on 14 October
2009 (Ref.: LLNSJV/2009/DC20074/000352) and a letter dated 22 January 2010
(Ref: (DC/2007/24)/M45/150(0018)) attached in Annex A of Appendix D.
(b) Reported cut by others on 9 October
2009. Refer to a letter dated on 14
October 2009 (Leighton Ref.: LLNSJV/2009/DC200724/000352) and a letter dated 22
January 2010 (Ref: (DC/2007/24)/M45/150(0018)) attached in Annex A of Appendix
D.
(c) Reported removed after typhoon on 16
September 2009. Refer to a letter
dated on 26 September 2009 (Leighton Ref.:
LLNSJV/2009/DC200724/000275) and a letter dated 22 January 2010 (Ref:
(DC/2007/24)/M45/150(0018)) attached in Annex A of Appendix D.
Landscape Character Areas (LCAs)
No
change in the updated baseline condition of LCAs (LCA1 to LCA5, LCA8 to LCA13) recorded in the recent review.
Visually
Sensitive Receivers (VSRs)
No
substantial change was observed except one identified VSR in
The Event and Action Plan in the
event of an exceedance of the above Action and Limit Levels are provided in Table 4.4 below.
Table 4.4 Event and Action Plan for Landscape and
Visual Impact - Construction Phase
Action Level |
Environmental Team Leader (ETL) |
Independent Environmental Checker (IEC) |
Engineerˇ¦s Representative (ER) |
Contractor |
Non-conformity on one occasion |
1. Identify source 2. Inform the IEC and the ER 3. Discuss remedial actions with the IEC, the ER and the Contractor 4. Monitor remedial action until rectification has been completed |
1. Check report 2. Check the Contractorˇ¦s working method 3. Discuss with the ER and the Contractor on possible remedial measures 4. Advise the ER on effectiveness of proposed remedial measures |
1.
Notify the Contractor 2.
Ensure remedial measures are properly
implemented |
1.
Amend working methods 2.
Rectify damage and undertake remedial measures
or any necessary replacement |
Repeated Non-conformity |
1. Identify source 2. Inform the IEC and the ER 3. Increase monitoring (site audit) frequency 4. Discuss remedial actions with the IEC, the ER and the Contractor 5. Monitor remedial actions until rectification has been completed 6. If exceedance stops, cease additional monitoring (site audit) |
1.
Check report 2.
Check the Contractorˇ¦s working method 3.
Discuss with the ER and the Contractor on
possible remedial measures 4.
Advise the ER on effectiveness of proposed
remedial measures 5.
Supervise implementation of remedial measures |
1.
Notify the Contractor 2.
Ensure remedial measures are properly
implemented |
1.
Amend working methods 2.
Rectify damage and undertake remedial measures
or any necessary replacement |
This
Baseline Environmental Monitoring Report has been prepared by Atkins China Ltd
(ACL) for Contract No. DC/2007/24 Construction of Sewage Conveyance System from
Apart from the construction works conducted by the Hong Kong West
Drainage Tunnel at the vicinity of Project Cyberport PTW site, no major
construction activities influencing air quality, noise or landscape and visual
aspects were identified during the baseline monitoring.
Baseline air quality monitoring was undertaken at four representative sensitive receiver locations, (CM_FM1 Western Wholesale Food Market, CM_CB1a The Arcade, Cyberport, CM_WF1a Wah Ming House and CM_AB1a The Hong Kong Ice and Cold Storage). The baseline monitoring of air quality included 1-hour and 24-hour TSP monitoring, which was undertaken from September to December 2009. The baseline TSP monitoring data was processed, reviewed and analysed to establish the appropriate Action and Limit Levels for 1-hour and 24-hour TSP during impact monitoring throughout the construction of the Project. The Projectˇ¦s Action and Limit Levels have been established in this report.
Baseline
noise monitoring for five locations (M3 Block A, Kwan Yick Building Phase III,
M5 Chuk Lam Ming Tong, M6a Outside of Aegean Terrace, M7a Wah Ming House and M8
Wah Lai House) have been completed to date (between September to November 2009).
The baseline monitoring included 24-hour noise monitoring, covering daytime,
evening-time and night-time periods.
Action and Limit Levels for the Project have been set.
Baseline landscape and
visual monitoring was conducted on 2 December 2009. The changes of existing baseline
condition of LRs, LCAs and views towards VSRs as stipulated in the approved EIA
were listed. Regular monitoring throughout
the construction period shall be undertaken as per the Event and Action Plan.